Blink and you’ll miss it! Malvern East II is changing so rapidly it’s hard to keep up. A few weeks ago when we visited the site for our update, they were completing the level one pour. Now only two weeks on and the precast concrete panels have been installed. 

In addition to this the team have been working hard on installing all the necessary scaffolding, so they can keep building up!

Today, we could walk on level one! Currently, the team is preparing all the formwork and getting ready for the level one pour next week. 

In the coming weeks, the level two precast panels will also be installed and the electrical works will commence from the lower basement. The level one stairs and lift formwork will also be beginning.

Watch this space and stay up to date with everything that’s happening at the Malvern East site. There are still a few remaining 2 & 3 bedroom apartments left on this project, to register your interest and for more information fill out the form below.

Disclaimer: The information and materials on this website, associated websites, blogs, social media, any other affiliated content or materials, are general in nature only and readers, viewers and consumers are advised to perform their own research and investigations and obtain their own financial, legal and other advice. This information and these materials do not form any representation by any vendors or agents of any vendors and may include third-party opinions that do not represent the opinion of any vendor or agent. The information and materials do not constitute legal, financial or real estate advice and must not be regarded or relied upon as such. None of it forms part of any contract of sale or vendor statement. Usage of this website and any associated website is subject to further terms and conditions.